What to Include

Build the bathroom as it will be handed over, not as a display. That means the vanity with its top, basin and tapware connected and running; the mirror and its lighting on the real circuit; the bathtub or shower enclosure installed on the finished floor and walls, with the drain in its actual position; the accessories, the ventilation and the tiling and waterproofing behind all of it. Use the approved samples and the production-intent products, not showroom units. Where the project has more than one bathroom type, the mock-up should cover the type that repeats most, and the variants can often be checked as partial mock-ups against it.
- All fixtures installed and connected on finished walls and floors
- Production-intent products and approved samples, not display units
- Services, lighting, ventilation and accessories in their real positions
- The most-repeated bathroom type first; variants as partial mock-ups
The Walk-Through and Sign-Off
The mock-up is reviewed by everyone with a decision to make: the designer for intent, the operator for how the room will be cleaned and maintained, the contractor for installation sequence and access, and the supplier for the products and their drawings. Each walks the room with a checklist — reach, clearance, door swings, service access, finish transitions, sealant joints, how the housekeeping cart gets in — and every observation is recorded with a decision: accept, change, or investigate. The sign-off is that record, dated and agreed, not a verbal approval. The changes it contains are the ones that would otherwise have surfaced on site later, one room at a time.
- Designer, operator, contractor and supplier each review against a checklist
- Reach, clearance, swings, service access, transitions and cleaning access
- Every observation recorded as accept, change or investigate
- Sign-off is a dated, agreed document
Feeding Production

The value of the mock-up is realized only if its decisions travel into production. Every agreed change is written into revised drawings and, where it affects a product, a revised sample sign-off — a moved drain, a changed hinge side, a different upstand height. Production is released against those revised documents, not the originals. The mock-up room itself is then kept as the physical reference: the first production units are compared to it, the site team uses it to brief installers, and the operator uses it to train housekeeping. On a phased project it stays in place until the last phase is installed.
- Agreed changes go into revised drawings and sample sign-offs
- Production is released against the revised documents
- The room becomes the quality and training reference
- Keep it until the final phase is installed