Chinese New Year

The Lunar New Year is the single largest disruption in the production year. Its date moves — it falls between late January and mid-February depending on the year — and the effect on a factory is longer than the official holiday. Production typically slows in the final weeks before the closure as orders are pushed through and staff begin to travel; the factory then closes for a period that commonly runs longer than the public holiday itself; and output ramps back gradually afterward as workers return, with some staff turnover every year. For a buyer, that means an order released close to the holiday may not start production until after it, and an order in production across the holiday will pause and then restart at reduced pace.
- Date varies by year: late January to mid-February
- Slowdown before, closure during, gradual restart after
- Orders released near the holiday may not start until after it
- Confirm the factory's actual closure dates for the specific year
The Other Seasonal Pressures
Two more pressure points sit on the calendar. The National Day holiday at the start of October is a shorter closure, but it interrupts production and shipping for around a week and is worth planning around for orders due in the fourth quarter. And shipping capacity itself is seasonal: the run-up to the western year-end retail season tightens space and lifts rates from late summer, and the weeks before Chinese New Year are a second peak as exporters clear orders before the closure. A booking made late into either peak may not get the sailing it wanted, regardless of when production finished.
- National Day in early October: a shorter closure affecting Q4 orders
- Late-summer to year-end: shipping peak driven by retail seasons
- Pre-Chinese-New-Year: a second shipping peak as exporters clear orders
Planning Around the Cycle

Work backwards from the installation date, as any import timeline should, and then check where each stage lands against the calendar. If production would straddle a holiday, either release earlier so that production, inspection and booking all complete before it, or accept that the timeline extends past the restart and plan the site accordingly. Production lead time remains subject to the current production schedule — typically 45–60 days — and the factory's loading before a holiday is exactly the condition that pushes it toward the longer end, so confirm it for the specific release date rather than assuming. Book freight early in a peak. And for a project with several phases, consider consolidating the production release before a holiday even if delivery is staged afterward.
- Plan backwards, then check each stage against the holiday calendar
- Release early enough for inspection and booking to precede a closure
- Confirm lead time for the actual release date — pre-holiday loading extends it
- Book freight early in a peak; consolidate releases where a project allows









