What to Check per Product Line

The checklist comes from the approved drawing and the golden sample, and it differs by line. Vanity: overall dimensions against the drawing, finish against the sample under the same light, hardware fitted as specified by model and operating, drawer fronts aligned and doors closing evenly. Top or basin: drain center and tap hole positions against the drawing, edge profile, color and surface against the sample, fit to its cabinet. Solid surface bathtub: drain and overflow position, which is cast and cannot be corrected later, surface finish and color, overall dimensions, and weight against the drawing.
Shower enclosure: panel sizes and glass thickness against the drawing, hole positions for hinges and handles, hardware fitted and operating, profiles and seals as specified, finish against the sample. For coordinated products such as faucets, shower systems and toilets, the same logic applies at the partner factory. The checklist records what was measured or compared, the result, and a photograph.
- Vanity: dimensions, finish match, hardware fit, drawer and door alignment
- Top or basin: drain center, tap holes, edge, color and surface
- Bathtub: drain and overflow position, surface, dimensions, weight as drawn
- Enclosure: panel sizes, hole positions, hardware fit, profiles and seals
Who Performs It and How

Factory quality control performs the first article check on a well-run line, and its record should be available to the buyer. A buyer who wants independence has three options: attend in person, rarely practical for a single unit; send a third-party inspector, effective but costly for one unit; or conduct it remotely, with the factory presenting the first unit on video or in photographs and measurements against the buyer's checklist, with the golden sample beside it. Remote review works well for bathroom fixtures because most checks are dimensional and visual.
Whichever method, the output is a completed checklist, photographs and a release decision. Release means production continues. Correct and re-check means the factory adjusts the set-up, material or process and presents another first unit. Stop means the difference is fundamental and the drawing or the sample has to be revisited. The first article unit is kept at the factory as the reference for the run.
- Factory QC performs it as standard; its record should be shared
- Independence by attendance, third party, or remote review with photographs and video
- Remote works because the checks are dimensional and visual
- Outcome: release, correct and re-check, or stop
FAI versus Pre-Shipment Inspection
First article inspection and pre-shipment AQL inspection answer different questions. FAI asks whether production is set up to make the product correctly; it looks at the first unit at the start of the run to prevent a repeated error. AQL inspection asks whether the finished lot is acceptable; it samples the lot after production, according to a sampling plan, to detect defects before shipment. FAI happens early enough to fix the process; AQL happens late enough to judge the result.
A project needs both. Without FAI, a systematic error is found at the AQL stage in every unit sampled, with the whole run made. Without AQL, an FAI-approved process still produces the occasional damaged unit or missing hardware kit that only a sample of the finished lot reveals. The golden sample is the reference for both. Sample approval, first article and pre-shipment inspection together are production control.
- FAI: first unit, start of the run, prevents repeated errors
- AQL: sampled finished lot, end of the run, detects defects before shipment
- Each answers a question the other cannot
- The golden sample is the reference for both